FORM
(For Revenue
authorities)
Gonda – Azimgarh Railway
AZIMGARH
SECTION
Schedule
showing land required for
railway purposes in
the Bilaspur tehsil
of the Banda district
Name of the village :- Mandwal
|
Reference to
Plan Set Sheets |
Purpose for which the land is occupied |
Area of land required (pink) |
|
Set-C 3 Banda District 3 3
4 4 4 5 6 6 |
Main line from chainage 36, 627 to chainage 38,900. Land to be permanently occupied Same length for side curttings Extra land for stocking material etc. at site of bridge No.57 Mandal Station yard Approach road to Mandwal Station Site for temporary house and office for Assistant Engineer Brickfield to north of line opposite chainage 42,350, to be permanently occupied Main line from chainage 41,440 to chainage 42,728, land to be permanently occupied Same length for side cuttings Total: |
Acres 4.6, 963 3.1, 309 9.5, 500 28.6, 961 2.7, 548 5.5, 096 11.2, 163 2.4, 389 1.5, 243 69.5, 172 |
Azimgarh: Executive Engineer
_____________ Engineer-in-Chief
General Manager ______________
Chief Engineer.
99. Paragraph 702 of the Indian Railway
Code- When the work
of acquisition extends to more than one district but lies within one division,
application should be made to the Commissioner, when in more than one division
to the Chief Revenue Authority of the State.
100. Paragraph
703 of the Indian Railway Code - For the better identification of land in cases where the areas to be
taken up are extensive, the following further information should also be
furnished by a Railway Administration to the State Government or Administration
in applying for the acquisition of land:-
(a)
The
name of the railway.
(b)
The
copy of the order of Government, when necessary, sanctioning the construction
of the railway.
(c)
A brief
general description of the route to be followed by the railway with the names
of the more important villages or towns through or near which it is intended
that the railway should pass.
(d)
A list
of the civil districts in which the land will be required for the purposes of
the railway with the approximate area in acres of the land required in each.
(e)
For
each civil district, the name or description of the place or places at which
the land plans for the district will be available for inspection by the public.
The State Government or
Administration should also be furnished with a general index plan to a scale of
1 mile to 1 inch showing the route to
be followed by the railway.
101. Paragraph 705 of the Indian Railway
Code - Should any
land be required for temporary occupation only under section 35 of Act 1 of
1894, it should form the subject of a separate application in which the fact
that permanent acquisition is not required should be clearly stated.
102. Estimates preliminary to putting
Land Acquisition Act into force – (Paragraphs 706 and 707 of the Indian Railway
Code)- On receipt from the Railway
Administration of the application for land drawn up in accordance with the
procedure prescribed above, the responsible Revenue Official will forward to
the Railway Administration a statement showing the nearest approximate cost of
the land which can be obtained without a detailed valuation of the property and
also a draft declaration under section 6 of the Land Acquisition Act on which
it should be recorded that there is no objection to the acquisition of land on
any general or specific grounds. In the
case of large projects, in lieu of the statement prescribed above, the Revenue
Authorities will furnish to the Railway Administration data in the form given in
paragraph 12 supra showing the
estimated average value per acre as near as may be for the different classes of
land in the localities affected by the projects.
In no circumstances should the Local
Revenue Authority be called upon to furnish data even rough approximations,
before they are supplied with a sketch map (or detailed plans, if such have
already been prepared), for each district traversed by the railway, showing the
exact course of the centre line of the land to be taken up, with reference to villages
and towns, as a departure from the strict observance of this requirement throws
upon the Revenue Authorities undue responsibility for the adequacy of the
preliminary estimates. The sketch map
should be to a scale of one inch to the mile and should show village boundaries
wherever they have been surveyed. The
distances should also be marked upon it, and the average width of the strip to
be taken up should be stated. For the
land near towns, or which for other reasons is likely to have specially high
value, a map to a sufficiently large scale should be prepared, showing the
approximate boundaries of the land likely to be required, with a note of any
valuable trees, buildings or other property for which compensation will have to
be paid in addition to the price of the land itself.
103. Paragraph
708 of the Indian Railway Code- When the estimated value of the land exceeds Rs. 25,000 in any one
district or one lakh in any division, it is necessary that the data should be
countersigned by the Commissioner of the division in which the land is situated
or the Chief Revenue Authority of the State, respectively.
104. Paragraph
709 of the Indian Railway Code - The statement or data received from the Revenue Authorities should be
taken as representing the value of the
land, inclusive of tenants rights but exclusive of the value of houses, trees,
standing crops, etc. on the land, the approximate cost of which should be
separately furnished by the Revenue Authorities. In addition to the data prescribed above, the Revenue Authorities
should also give a rough estimate of the amount of such further
items (if any as are likely to be included in an award based on section 23(I)
of the Land Acquisition Act, including when necessary, and estimate of payments
to be made direct to the proprietors of the area acquired in lieu of abatement
of land revenue and charges for establishment and contingencies. Special care should be taken by the Revenue
Authorities in furnishing as accurate data as possible, so as to prevent inaccurate
estimating. With this information in
hand, the Railway Administration should proceed to frame an estimate* of the
total cost of acquisition in detail, including (in cases where voluntary
surrender is not probable) the additional 30 per cent laid down in section
23(2) of the Land Acquisition Act, on the market value of the land under
section 23(I), clause I of that Act.
104-A. Form for preparing land
estimates - In
preparing land estimates, it will be found generally convenient to adopt the
following form:-
Value of land:--
Waste
Arable
Homestead
Bazar
*In the reports and estimates submitted by Railway Administrations, it should be specially mentioned whether or not the land estimates have been prepared from data furnished by the Revenue Authorities.
Value
of:--
(a)
Masonry
houses
(b)
Thatched
houses
(c)
Trees
(d)
Standing
crops
Add additional compensation at 30
per cent under section 23(2) of the Act on the market value of the land
including houses, trees and crops,
Add
market value of Government land taken up.
Add
damages under clauses 2 to 6 section 23 (I) of the Act.
Add
cost of establishment (when necessary).
Add
contingencies.
105. Paragraph
711 of the Indian Railway Code- Should the estimate so framed be within the powers of the Railway Administration
to sanction and there be no objection to the acquisition of the land on the
part of the revenue authorities, the General Manager or any other Officer duly
empowered to sanction the estimate will then accord sanction and allot the
necessary funds and forward the estimate duly countersigned by the Accounts
Officer together with the draft declaration and duly signed plans and
schedules, to the State Government or
Administration for taking necessary steps for the acquisition of the land. When
it is decided to make reduction in the extent of the land which the State
Government has already been asked to arrange to acquire prompt warning should
be given to them to take steps to modify the declaration already issued, or to
make necessary withdrawal from acquisition.
If the sanction of the Railway Board is necessary to the estimated cost
of the land, the Railway Administration should apply for and obtain that
sanction before applying to the State Government or Administration for the
acquisition of the land.
105-A. Act XXXVIII of 1923
Notification under section 4- After receipt of such an application the State Government or
Administration Act XXXVIII of 1923, will issue a notification under section 4 whether
a preliminary survey notification under section 4, or other Act provided for in
section 4 is necessary or not. A copy
of this notification shall be pasted at the Collectors Office and at the Tehsil
and shall be served on all persons known to be interested who would be entitled
to claim an interest in the land acquired under the Act.
Note: All owners, mortgagees and tenants whether occupancy or not,
should ordinarily be included in the term “persons interested” for the purpose
of this rule.
105-B(a) (Act XXXVIII of 1923,
Disposal of Objections)-Any person interested in any land which has been notified under section
4, sub-section (1) may within 30 days after the issue of the notification
object to the acquisition of the land or any land in the locality as the case
may be. Every such objection must be
made to the Collector in writing and the following procedure is to be observed
for the disposal thereof: -
(i)
When
the Collector receives an objection, he shall fix a date for hearing it, and
shall give notice of the date to the objector and to the officer of the
department or to the local body on whose application the notification under
section 4 has been issued. It will
generally be convenient to hear all objections after a limit of thirty days has
expired.
(ii)
On the
date fixed for hearing, if the objector fails to appear in person or by
pleader, the Collector, may if he thinks fit make an ex parte enquiry regarding the objection, or he may at once report
to the State Government the fact of the objector’s failure to appear. In either case he shall without unnecessary
delay, report his opinion as to the validity of each ground of the objection.
(iii)
The
Collector shall forward his report together with the record of his proceedings
direct to the Home Secretary to the Punjab Government.
(iv)
No
costs shall be allowed.
(b) If
the State Government after considering of the report of the Collector decides
to withdraw from the acquisition proceedings, the notification under section 4
of the Act shall be cancelled without delay.
106. Procedure
in cases of urgency- (Paragraph
714 of the Indian Railway Code) - In cases of urgency, Railway
Administration are empowered to depart from the ordinary rule stated in the
previous paragraph and sanction the acquisition of land prior to the
preparation and sanction of estimates either for the work of the land, provided
the total probable cost of the work is within the power of Railway
Administration to sanction. Where it is
anticipated that the estimated cost of the land or the work will exceed the
powers of sanction of the Railway Administration, the reasons for urgency of
acquisition and brief particular of the work for which it is required together
with information regarding the probable cost of the land and of the work should
be reported to the Railway Board and their sanction to the acquisition of the
land applied for.
107. Where
land is granted free of cost, Government undertake to secure to the railway
only empty possession- (Paragraph 717 of the Indian Railways Code) - Where land
is acquired by Government and made over free of cost to a Railway Company, for
the construction of a Railway, the Railway Company, in the absence of any
express stipulation to the contrary, are entitled to dispose of, or use for the
purpose of the railway and material, trees, buildings or other property that
may be on the land when it is handed over to them, but Government are entitled,
before handing over the land, to dispose of or stipulate for the disposal of,
any such material, trees, buildings, etc. which they may have been obliged to
acquire with the land and to apply the sale-proceeds in reduction of the cost
of acquisition. Further, it is the
business of the Railway Company to clear the land of all obstacles or
obstructions and prepare it for the construction of the railway, Government
undertaking to secure to them empty possession only free of encumbrances.
(c) Procedure after the Act
is put into force
108. After
publication of declaration – (Paragraph 718 of the Indian Railway Code)- After the publication of the declaration under
section 6 of the Land Acquisition Act, the State Government or Administration
will direct the Collector, or other
Officer specially appointed for the purpose, to proceed to acquire the
land in the manner indicated in the Land Acquisition Act and all subsequent
proceedings will be taken by the State Government or Administration. When the awards have been announced, the
Railway Administration may enter into possession of the land, but before doing so, the authority of the Land
Acquisition Officer to its occupation should be obtained. When possession is taken, the acquisition is
completed and the land then vests absolutely in Government. Up to the moment of
taking possession under the Act, Government is at liberty to withdraw from the
acquisition but not afterwards. It should be noted that withdrawal from
acquisition entails liability for payment of compensation for any damage
suffered by the owner in consequence of the notice or any proceedings
thereunder. [Section 48(2) of the Land Acquisition Act].
109. Valuation
for purposes of the award – (paragraphs 719 & 720 of the
Indian Railway Code) - A Land Acquisition Officer in any inquiry and
award under section 11 of the Land Acquisition Act, will give notice to the
Railway Administration or their chief local representative of the day on which
the enquiry is to be held, and will take into consideration any representation
which the Railway Administration or their chief local representative may make
whether orally or by letter. Also
before finally making the award, the Land Acquisition Officer will allow the
Railway Authorities an opportunity of appearing in person or by agent and of
producing evidence as to the value of the land. Railway Administration should take advantage of these
opportunities for representing their views and protecting their interests. Further, in order to protect the interests
of Government in cases where land is granted free of cost to a railway, it is
incumbent on the Collector of the District, or should he himself not be making
the award, the Land Acquisition Officer so authorised to refer to the Officer
nominated as Government Director of the Circle or the General Manager of the
Railway Administration or his representative, all cases in which the awards are
likely to exceed the original estimates by more than 10 per cent or by more
than Rs.10,000. The officer nominated
as Government Director or the General Manager of the Railway should then decide
whether it is advisable to be present, and if so, he should inform the
Collector or the Land Acquisition Officer (through the Collector) to that effect within one month of the date of the
receipt of the reference. If no such
intimation is received by that date, it should be assumed by the Collector that
the officer nominated as Government Director or the General Manager does not
want to be present and that there is no objection to the award being then
made. It is very important that the
procedure herein above laid down is taken advantage of in order that the
interests of the purchaser may be adequately represented.
If the award, as finally settled
after objections have been heard in the course of proceedings, exceeds by more
than 20 per cent the original estimate of the cost of acquisition or if the
evidence as to the value is conflicting and such as to indicate a reasonable
probability that the Civil Court will award a sum exceeding that estimate, the
Land Acquisition Officer should defer the award and inform the Railway
Administration concerned of the facts.
Further action will then be suspended until the Railway Administration
has decided whether acquisition should be proceeded with or not. Before communicating such decision the
Railway Administration should, when the
excess is likely to exceed their powers of sanction, submit a report of the
matter for the orders of the Railway Board, explaining at the same time whether
the acquisition of the land is necessary or whether some plot of land other
than that originally contemplated may not be taken up instead. It is incumbent on Railway Administration to
endeavour to avoid the location of a railway line upon land the acquisition of
which will entail either unnecessary expenditure to Government, or annoyance to
the owners, if the object sought can be equally well attained by a slight
alteration of the alignment or in some other manner.
109-A. Taking possession – (paragraphs 721 & 722 of the
Indian Railway Code)- Possession of the Land will be made over by the Local Revenue Authority
or his representative and will be taken over by a representative not lower in
status than a Sub-Divisional Officer of the Engineering Department of the
Railway. The area on the ground should
be carefully checked with that on the Plan, and if found correct, the permanent
boundary marks should be affixed as soon as possible thereafter.
A certificate, atleast in duplicate,
to the effect that the land has been on that day correctly made and taken over,
will then be signed by both parties and recorded by the Revenue and Railway
Authorities, respectively.
110. Revised
estimates –(Paragraph
723 of the Indian Railway Code) - If during the proceedings under section 11 of the Land Acquisition Act,
it becomes apparent to the Land Acquisition Officer that the cost of the land
will exceed the amount of the sanctioned estimate, he should report the excess
to the Railway Administration concerned and at the same time furnish fresh data
for the revision of the estimate. The
Railway Administration will then frame a revised estimate of cost in full
detail and if the excess is within the powers delegated to the Railway
Administration, sanction the estimate and allot the further funds
necessary. Should the revised estimate,
however, require the sanction of the Railway Board, such sanction should be
applied for, in doing so, an explanation of the cause of excess should be
furnished, where it exceeds the initial estimate by more than 10 per cent. It should be noted that the countersignature
of responsible Revenue Authorities should be obtained to the revised estimate
as in the case of the original estimates.
110-A. Completion Reports – (Paragraphs 724 & 725 of the Indian
Railway Code) - When acquisition has been finally completed and awards
made, a completion report showing the actual expenditure incurred on the
acquisition should in the case of lines under construction, and of open line
works costing Rs.20 lakhs and over, be submitted to the Railway Board, either
separately or along with the completion report of the works for which the land
has been acquired. These completion
reports should be drawn up in details by the Railway Administration on the
awards actually made. As regards land
taken up for open line works costing less than Rs.20 lakhs, no completion
report need be submitted to the Railway Board unless it is found that
expenditure has been incurred over the original or revised estimate, in excess
of the power of the Railway Administration.
111. (Paragraph 810 of the Indian
Railway Code) -
A State Government may be offered the management of such areas of “available”
land as it may agree to accept and if necessary may be permitted to retain a
percentage (to be agreed upon between the Railway Administration and the State
Government) of the gross receipts accruing from the lease etc. of the
land. In such cases the following
conditions will apply, viz: -
(i)
That
such transfer conveys no power to sell, exchange or give away the land without the
sanction of the Railway Administration (i.e. the land will still remain in the
“occupation” of the Central Government), and that the latter may impose such
restrictions as it may consider necessary on the use or occupation of the land
so entrusted.
(ii)
That
the Railway Administration reserves the right to withdraw such land, without
compensation after giving reasonable notice or on payment of a fair price if
resumption is made at such short notice as to preclude the gathering of any
crop, indigenous to the locality, sown thereon.
(iii)
Receipts,
less any percentage that may be agreed
upon, will be credited to the Railway.
Taxes, which would be leviable on the land were retained under the
management of the Railway Administration, will continue to be a charge on the
Railway.
(iv)
That
on the resumption of the land by the Railway Administration or if under
disposal on its sale, it should be handed over with a clear title, any steps
necessary to preserve such title being taken by the State Government on behalf
of the President.
Land
made over for management to the State Government should be properly demarcated
and accompanied by the necessary plans.
112. Methods of
Management – (Paragraphs 812, 813, 814 and 815 of the Indian
Railway Code): --To
enable management to be conducted on commercial lines, Railway Administration are permitted to grant to outsiders
or other Departments, under a lease or license, rights and facilities in
respect of “available” land for such purposes, whether or not connected with
Railway working, as they may deem suitable.
The
leasing or licensing of “available” land agreeably to these rules, for purposes
connected with the working of the Railway (e.g. Bulk Oil Installations;
Warehouses, Wharfs or other premises for storing goods on receipt from the
Railway after arrival or before being made over to the Railway for dispatch;
Shops for Station Vendors; Schools for the children of railway employees, etc.
etc.) does not require a reference to a
State Government or other authority; but, in the case of land leased or
licensed for other purposes, the State Government or other authority concerned
should be consulted whenever the contingent circumstances are such as to render
it relevant or advisable, particularly if the alienation is of a quasi-permanent
nature.
The
leasing or licensing of Railway land for religious or educational purposes or
the granting of permission for the erection on railway land of new structures
to be used for religious purposes or the modification or extension of existing
structures, will require the sanction of the Railway Board. The General Manager of a Railway is,
however, empowered to license plots of vacant railway land to railway employees
for the purposes of “praying platforms”.
In
addition to the lease or license of land itself, rights pertaining thereto,
such as grass-cutting, grazing, fruit, fishing, mooring, etc. may be let out by
Railway Administration.
113. Paragraph
816 of the Indian Railway Code- The method by which land is managed by a State Government will be
decided by that authority, subject only to the conditions on which such
management is undertaken.
114. Paragraphs
801, 823 and 824 of the Indian Railway Code- The instructions in this section are subsidiary
to the land Transfer Rules issued by the Government of India and contained in
paragraph 2 supra.
The general position is that under
section 172 of the Government of India Act, 1935, relevant portions of which
are reproduced below, all lands and buildings which vested in His Majesty
immediately before 1st April, 1937, and which were then used
(otherwise than under a tenancy agreement between the Central and State
Government) for purposes which thereafter became purposes of the Central
Government (e.g. for the purposes of Federal Railway) would automatically vest
in the Central Government. Lands and
buildings, which were not actually so used immediately before 1st
April, 1937, even though formerly intended to be used for Central purposes,
would vest in the provinces, unless they are certified to have been retained
for future use for Central purposes or to have been retained temporarily for
more advantageous disposal by sale or otherwise. Under this section, therefore,
Railway Administrations have the right to remain in undisturbed possession of
only such lands in their occupation on the 31st March 1937 as were
actually required for the effective discharge of their duties (of paragraph 825
infra).
“Section
172 of the Government of India Act, 1935—(1) All lands and buildings which
immediately before the commencement of Part III of this Act were vested in His
Majesty for the purposes of the Government of India shall as from that date:
(a)
In the
case of lands and buildings which are situated in a province vest in His
Majesty for the purposes of the Government of that Province unless they were
then used, otherwise than under a tenancy agreement between the
Governor-General in Council and the Government of that Province, for purposes
which thereafter will be purposes of the Federal Government or of His Majesty’s
Representative for the exercise of the functions of the Crown in its relations
with Indian States, or unless they are lands and buildings formerly used for
such purposes, as aforesaid, or intended or formerly intended to be so used,
and are certified by the Governor-General in
Council, or, as the case may be,
His Majesty’s representative, to have been retained for further use for such
purposes or to have been retained temporarily, for the purpose of more advantageous
disposal by sale or otherwise.
(b)
in the
case of lands and buildings which are situated in a Province but do not by
virtue of the preceding paragraph vest in His Majesty for the purposes of the
Government of that Province, and in the case of lands and buildings which are
situated in India elsewhere than in a Province, vest in His Majesty for the
purposes of the Government of the
Federation or for the purposes of the exercise of the functions of the
Crown in its relations with Indian States, according to the purposes for which
they were used immediately before the commencement of Part III of this Act;
XX XX XX XX XX
(5)
Any
question which may arise within the five years next following the
commencement of Part III of this Act as
to the purposes for which any lands or buildings are by virtue of this section
vested in His Majesty may be determined by His Majesty in Council.”
In regard to all railway land the
policy of the Railway Board is to limit holdings to actual requirements,
present and prospective. Every Railway Administration, should, therefore, be in
a position to justify the retention of land occupied by them, and where unable
to do so, should classify it as “eligible for disposal” and arrange for its
disposal agreeably to the rules in the following paragraphs.
While land is not to be retained
unreasonably, it is equally not to be disposed of and prices in commensurate
with its value, nor surrendered free of cost.
115. Paragraph
825 of the Indian Railway Code - In deciding whether or not a certain area is eligible for disposal,
Railway Administration should be guided by the consideration that land may be
said to be required for the effective discharge of the duties of the Ministry
of Railway, if it falls within one or the other of the following categories: -
(a)
Land
in the active occupation of a railway, i.e., land actually occupied by the
permanent works of the railway, or required for their construction, maintenance
or repair.
(b)
Land
not so occupied, but to the permanent alien control of which specific
objections exist, i.e., land in the midst of or adjoining that in active
occupation and to separate which from such area would be detrimental to railway
interests.
(c)
Land
required in the interest of the health or welfare of the staff, or for the
safety of railway property (e.g. sanitary or fire zones, etc.).
(d)
Land
required for such future development as may properly be contemplated.
116. Paragraph
826 of the Indian Railway Code - When it has been decided that a certain area of land is no longer
required by any department of the railway and that it is, therefore, eligible
for disposal. The following procedure
should be observed: -
(1)
If the
land adjoins or is in the near vicinity of land belonging to any other railway
or department of the Central Government it should first be offered to such
railway or department. If one of these
desires to acquire it, the land should on the terms being agreed upon, be made
over by the responsible railway authority to an officer of the department or
railway deputed for the purpose. A
formal record of the transfer should be made and the State Government advised;
or if willing, the latter may be entrusted with the work of transfer.
(2)
If the land is not adjacent to or in the close vicinity of that held by other
railways or departments of the Central Government or, though so situated, is
not required by such railways or departments; it should be offered to the State
Government. If the State Government is
willing to purchase it, it should on the terms being agreed upon, be made over
to the officer appointed for the purpose, the procedure laid down in paragraphs
109 and 109-A, supra, being followed mutatis mutandis.
(3)
If the
State Government is unwilling to purchase it, the land should be disposed of to
the best advantage possible.
(4)
If
neither another railway nor a department of the Central Government nor the
State Government, desire to acquire the land, and if no reasonable offer is forthcoming
from other parties, the land should be retained by the Railway Administration
and managed in accordance with the procedure laid down in paragraph 807 of the
Indian Railway Code for the Engineering Department, until such time as one or
the other of the above contingencies eventuate.
116-A. (Paragraph 827 of the Indian Railway Code)- In the disposal of land under clause (3) of the preceding
paragraph, the following procedure should be adopted :-
(a)
The
State Government may be asked to undertake the whole process of disposal, the
Railway Administration merely concurring in the terms.
(b)
If the
State Government is unwilling to undertake negotiations for sale these should
be carried out by the Railway Administration and the State Government requested
to carry out by the final transaction on the terms arranged.
(c)
If the
State Government is unwilling to effect even the actual transfer, a formal deed
of conveyance should be drawn up by the Railway Administration (ordinarily at
the expense of the purchaser), submitted to the authority competent to execute
it for signature, and registered, the land being thereafter made over, by the
responsible authority to the purchasers.
(d)
In any
case the State Government should be consulted as to the manner of disposal, the
conditions (if any) that should be laid down for the use of the land after
sale, and the extent to which (if at all) the principles of the Resolution of
the Government of India in the Department of Revenue and Agriculture
No.13/44-13, dated 30th October 1896, reproduced below, should be
applied: -
Resolution No.13/44-13, dated 30th
October, 1896 of the Government of India in the Department of Revenue and
Agriculture. The Government of India
desire that whenever agricultural or pastoral land has been acquired for public
purposes, whether by private purchase or by compulsory acquisition, and is no
longer required for such purposes, the disposal of it may be guided by the
following general considerations:-
“In the
first place all proprietary rights and all rights of occupancy which were
extinguished by the acquisition should be first offered to the persons from
whom they were acquired, or their heirs if discoverable; the former (where both
kinds of rights co-existed) being made subject to the latter under the provisions
of the Crown Grants (Act XV of 1895).
“In the
second place of the price at which these rights are offered should be the
amount of compensation originally paid
for them, less the 30 per cent in excess of the value which will have been paid
if the acquisition was compulsory. This
price may be reduced, if necessary, on account of any deterioration that may
have taken place in the fitness of the land for agricultural or pastoral
purposes while it was in occupation of Government, but it should not be
increased, except in the case stated below, on account of any rise in its
market value during that period.
“In the
case of plots which by reasons of their size or shape are practically of no value
to anyone but the owners of the adjoining land of those owners are not entitled
to the first offer as above, they ought nevertheless to receive the first
offer; but in that case there is no objection to asking the market value,
though the reasonable offer of a neighbouring holder should always have the
preference over that of an outsider.
“The
Superior Revenue Authority will, of course, always retain and exercise
discretion in the application of the general rule about the charge of cost
price. Special Cases will occur, and
exceptions will be justifiable, as for example, when the persons first entitled
are remote descendants or relations of the original holders, or when the rise
in the market value of the land has been so exceptionally great as to take the
case out of the general rule. The
Government of India lay down no hard and fast rule, but only a principle for
general guidance.
“It
will be observed that the above principles apply to agricultural and pastoral
land only, and not to building sites or town lands.”
“2. It
will be for Local Governments and Administrations to issue instructions adopted
to local circumstances, in general conformity with the above
considerations. Those instructions will
be mere executive instructions; and the
greatest care should be taken to avoid anything which might have the semblance
of conferring a right, or affording a basis for any claim either as against
Government or as between private parties, and to make it clear that the concessions in question are made as an act of
grace, and are wholly within the pleasure of Government to grant or to refuse
in any particular case.”